  1. Flip Book for Rare Manuscripts
    1. Project Lead: Gabriel
    2. Project Status
    3. Project Timeline: 
  2. Stone Classroom AV upgrade to include videoconferencing
    1. Project Lead: Matt
    2. Project Status
      1. Estimates from vendor obtained, ~$21,000
      2. Project send to CIT-Integrated AV for second quote, which costs $2,500. Has not yet been approved
      3. Ezra Delaney is looking for funding from CALS first, then if denied for CUL funding
    3. Timeline: Winter Break 2017 installation (tentative)