KFS Cutover Dress Rehearsal testing: DR#1 (5/2 - 5/13) & DR#2 (5/23 - 6/3)
As I had noted in my 02 28 2011 status report, we had discussed the Final QA period and Entry Criteria for testing at the 01/26/2011 and 02/09/2011 Leads Meeting. I believe much of the criteria is the same for the Dress Rehearsal period. System Test Plan Entrance Criteria .
KFS-PROD Technical
KFS-PROD delivered on 4/28 will be used for the Dress Rehearsal starting on 5/2.
...
- Connection pool is being expanded tonight.
- Long search times noted by Greg
- Dialogue just beginning with some key tech folks
- Orphaned eDocs resulting from the enterprise Cynergy merge
- Dialogue restarted with key tech folks on this (there is some history on this from our Cynergy merge experiences with KFS-DEV & KFS-TEST)
- Missing labor data that is blocking any labor testing (per Bob)
- Resolution may be imminent
- eShop integration doesn't doesn’t exist (that's that’s still in KFS-DEV)
- This won't won’t be in KFS-PROD for DR1
- No webMethods integrations are running (CoA, Position Data, Buildings & Rooms)
- Work continues on this front
...