See recovery project's punch list.

Update

11/1215/13

Draft schedule, assuming no surprises

Now: Yi to run 2 different ~24 hour tests.

...

, Friday

  • Matrix is now open to all researchers.

=> Researchers to confirm they have all their data from their clean-up. We recognize this may require running some test jobs. Do this as soon as possible!

Deadline for getting older files back is:

  • Monday, 11/25 (but may be sooner if spare HDs needed earlier!): After this date, we will be unable to restore any data not on EZ-Backup.

...

ChemIT's hard drive testing status.

...