Duration: About two days.

After moving is done, Liang will startaccess Eldor

Move other users' data from AFS to CIFS one by one.

Draft start date: Week of June 10. As CIFS added for user and data moved to CIFS, turn off AFS for that user.

Duration: About one-two weeks. Do quickly to reduce overlap of some folks on AFS and some folks on CIFS.

Turn off AFS (waiting

...

this late allows us to roll-back, if Eldor must be reverted)

Tentative date: Soon after Eldor is functionalDo soon after all accounts have been successfully moved to CIFS and have thus been turned off from AFS.

Status

Must identify all current users of Eldor

...