4/5/13 (Fri): Decision made that ChemIT will host new server for at least 6 months. This will provide ChemIT more time to work with Jack, Liang and others on pricing out alternative hosting options, but in the meantime putting the server back under support. This includes Lulu coordinating on the timing of the server's move and its new OS install with Liang (see to-do's).

Decision Liang and Peter have agreed to remove the graphic cards(computational) video cards before Lulu upgrades the OS.

To do's:

  • Lulu and Liang, with Barry, work out timing for when server gets moved from CCMR to ChemIT, and the necessary steps.
  • Lulu and Liang work out downtime required for Lulu to replace OS with an OS ChemIT can support.
  • Lulu and Liang to work out testing of server post OS change.
  • Lulu and Liang to work out service windows for Lulu to do necessary server administration tasks.

...

4/3/13: Oliver spoke with Liang and Peter. Liang and Peter approved removing the (computational) video (GPU) cards before Lulu upgrades the OS.

...