4/5/13 (Fri): Decision made that ChemIT will host new server for at least 6 months. This will provide ChemIT more time to work with Jack, Liang and others on pricing out alternative hosting options, but in the meantime putting the server back under support. This includes Lulu coordinating on the timing of the server's move and its new OS install with Liang (see to-do's).

Decision to remove the graphic cards.

To do's:

  • Lulu and Liang, with Barry, work out timing for when server gets moved from CCMR to ChemIT, and the necessary steps.
  • Lulu and Liang work out downtime required for Lulu to replace OS with an OS ChemIT can support.
  • Lulu and Liang to work out testing of server post OS change.
  • Lulu and Liang to work out service windows for Lulu to do necessary server administration tasks.

...

Project notes and efforts

4/3/13: Oliver spoke with Liang and Peter. Liang and Peter approved removing the video cards before Lulu upgrades the OS.

As of January, ACERT not charged by CCMR. This means the server is not being supported so we should move that server under support sooner than later.

...